What will my house cost?
A quick, honest range for your plot — with materials, stages and the pros you'll need.
- 1Step 1 of 4: Plot
- 2Step 2 of 4:
- 3Step 3 of 4:
- 4Step 4 of 4:
Plot
Floors
1,350 sq ft built per floor. Most Doon homes cover 70–80% of the plot.
Site
Basements cost ₹2,200–3,000/sq ft with waterproofing.
Quality
Construction quality
What should the rate cover?
Extras
Interiors
G+1 · Standard · Complete house · Dehradun
₹51.3–64.8 lakh
≈ ₹1,900–2,400/sq ft
2,700
sq ft built
1,350
sq ft per floor
≈41
weeks
Building
2,700 sq ft × ₹1,900–2,400/sq ft
₹51.3–64.8 lakh
Where the money goes
Typical split of the building cost for a standard house.
- Cement16%₹8.2–10.4 lakh
- Steel18%₹9.2–11.7 lakh
- Bricks & blocks7%₹3.6–4.5 lakh
- Sand & aggregate9%₹4.6–5.8 lakh
- Flooring & tiles8%₹4.1–5.2 lakh
- Paint5%₹2.6–3.2 lakh
- Plumbing & sanitary6%₹3.1–3.9 lakh
- Electrical6%₹3.1–3.9 lakh
- Doors & windows7%₹3.6–4.5 lakh
- Labour18%₹9.2–11.7 lakh
Materials you'll need
Thumb-rule quantities for your built-up area. Tap to shop on Nirmaan.
- Cement1,080–1,215 bagsShopShop Cement
- TMT steel9.5–12.2 tShopShop TMT steel
- Sand4,860 cftShopShop Sand
- Aggregate (rodi)3,645 cftShopShop Aggregate (rodi)
- Bricks21,600 nosShopShop Bricks
- Floor tiles2,970–3,510 sq ftShopShop Floor tiles
- Paint324–432 LShopShop Paint
Thumb rules only — your structural drawings and BOQ give the exact quantities.
Stages & payment schedule
About 41 weeks (~10 months) of work. Pay per finished stage.
- 1
Foundation & plinth
≈5 weeks · 15% of cost
₹7.7–9.7 lakh
- 2
RCC frame & slabs
≈13 weeks · 35% of cost
₹18.0–22.7 lakh
- 3
Brickwork & plaster
≈8 weeks · 20% of cost
₹10.3–13.0 lakh
- 4
Plumbing & electrical
≈4 weeks · 10% of cost
₹5.1–6.5 lakh
- 5
Flooring, paint & finishing
≈11 weeks · 20% of cost
₹10.3–13.0 lakh
Design, approvals & contingency
Budget for these on top of the building cost.
Architect & structural design
3–8% of construction cost
₹1.5–5.2 lakh
MDDA / HRDA map approval & fees
1–2%, varies by plot & authority
₹0.5–1.3 lakh
Contingency (price rises, changes)
keep 5–10% aside
₹2.6–6.5 lakh
GST on a contractor's bill
0% if you buy material yourself; up to 18% on a with-material contract
0–18%
All-in budget
Building + design, approvals and contingency (GST not included)
₹55.9–77.8 lakh
Who you'll need
Verified pros near you, by trade.